Migrating from Ensim 3.1

A

AndyD

Guest
I have one server with Ensim 3.1 in a different data centre to my other servers, so basically, I want to transfer all of the sites onto a new server which I have just installed with my other servers.

The new server has a fresh install of Debian on it, and I'm hoping to install Plesk 8.0 to match my other Plesk servers.

So my question is; how easy would it be to migrate the sites to Plesk?

The Ensim server is currently hosting about 60 sites, so doing it by hand would take a very long time.
 