• The BIND DNS server has already been deprecated and removed from Plesk for Windows.
    If a Plesk for Windows server is still using BIND, the upgrade to Plesk Obsidian 18.0.70 will be unavailable until the administrator switches the DNS server to Microsoft DNS. We strongly recommend transitioning to Microsoft DNS within the next 6 weeks, before the Plesk 18.0.70 release.
  • The Horde component is removed from Plesk Installer. We recommend switching to another webmail software supported in Plesk.

Proper procedure for upgrading to 8.0

PSi_101

Regular Pleskian
From experience I found that when upgrading within the 7.5.x series, it was best to upgrade the base package first before any other packages. For those that were successful with the upgrade, did you upgrade all the 8.0 packages at once? Or did you do the base package first followed by the others.
 
You should install all RPM's in the /base directory simultaneously to avoid problems. The /opt packages can be installed in any order.
 
Back