Issue ASP.NET Core support issue in Plesk 18.3

YISolutions

New Pleskian
Hi,
im using Asp.net Core 2.1 on Plesk 18.30 windows version but it has given this error

HTTP Error 502.5 - ANCM Out-Of-Process Startup Failure​

Common solutions to this issue:​

  • The application process failed to start
  • The application process started but then stopped
  • The application process started but failed to listen on the configured port

Troubleshooting steps:​

  • Check the system event log for error messages
  • Enable logging the application process' stdout messages
  • Attach a debugger to the application process and inspect

For more information visit: https://go.microsoft.com/fwlink/?LinkID=808681

 